
Talking About Risks
This issue of the CompanySmith newsletter will address
four barriers to communication of risks in projects.
1. There isnt time to work on risks
There are many fundamentals of leading projects. Early
in the project these traditionally include requirements definition, work
breakdown, task dependency, resource allocation etc. Late in the project
its management of the bug / punch list and completion of problem tasks.
I consider risk management an overlay to all of these
project steps. Projects need an escalation process when things are not going
per plan or the plan has gaping unknowns. Risk management is that process.
It is where the top issues are highlighted, defined, discussed, prioritized
and worked.
A one page risk management report and two page process
definition will keep the paperwork preparation time to a minimum. Discussion
with the stakeholders when the risks are reviewed provides most of the value
from the process.
The payback on risk management is the reduction of the
length of the project, and improvement in predictability of the end date.
2. Management will drive us nuts if we show them the risks
No doubt this can happen. The relationship between
management and the team is critical. If there is not sufficient trust or
respect, then team issues should be worked outside of the project in order
to build an environment where open discussion is not only possible, but is
the norm.
One approach is to focus on risk management as a
discussion tool, not a call for help or request for a decision. Sure, some
of the risks may come to asking management for help, but set the stage for
the risk management meeting as a working meeting.
3. We are working on all the risks we know about
Working issues is the job of project and product
development leaders. The added benefit of the risk management process is
that it provides prioritization and broader perspective on the issues than
is available from the core team.
The risk management plan should be reviewed by the
stakeholder team. The broader perspective of the stakeholders will alter the
priorities (raising or lowering them) and will also provide additional
perspective on the nature and substance of the risks, and what might be done
to mitigate them. The investment in talking about the project and its risks
will greatly improve project results.
4. We cant do anything about them anyway
That may well be true for some risks, but the majority
of risks can be reduced, eliminated, or agreed to be tolerated. For those
that cant be eliminated, the team usually can find steps to lower the
risks. That is always a benefit to the project and to the team.
There are always some risks that you cant eliminate.
The process of determining the financial impact of those risks will put them
into perspective. The perspective may be that the financial risk is
acceptable to the business. If it is not acceptable, then other steps might
include changing the project approach by changing the requirements, changing
the project scope, changing distribution, or in some cases, stopping the
project.
Concluding
Over the years I have seen many teams that have ignored
big risks. The most costly (and surprisingly common) three that I have seen
have been:
-
Developing a product without understanding which customers will want
it and write purchase orders for it
only to find that too-few customers are
interested.
-
Developing a product that customers want, but the company not having
a distribution channel to deliver it to the customers and then support the
product. (a variation of this problem is trying to put new product through a
sales channel that is well-paid and busy with another product line)
-
Continuing a project to release when the product cost was higher than
what the market would pay.

Home | Privacy